Solomon Ogyem – Media Entrepreneur | Journalist | Brand Ambassador
Solomon Ogyem is a dynamic Ghanaian journalist and media entrepreneur currently based in South Africa. With a solid foundation in journalism, Solomon is a graduate of the OTEC School of Journalism and Communication Studies in Ghana and Oxbridge Academy in South Africa.
He began his career as a reporter at OTEC 102.9 MHz in Kumasi, where he honed his skills in news reporting, community storytelling, and radio broadcasting. His passion for storytelling and dedication to the media industry led him to establish Press MltiMedia Company in South Africa—a growing platform committed to authentic African narratives and multimedia journalism.
Solomon is the founder and owner of Thepressradio.com, a news portal focused on delivering credible, timely, and engaging stories across Ghana and Africa. He also owns Press Global Tickets, a service-driven venture in the travel and logistics space, providing reliable ticketing services.
He previously owned two notable websites—Ghanaweb.mobi and ShowbizAfrica.net—both of which contributed to entertainment and socio-political discussions within Ghana’s digital space.
With a diverse background in media, digital journalism, and business, Solomon Ogyem is dedicated to telling impactful African stories, empowering youth through media, and building cross-continental media partnerships.
The KwaZulu-Natal department of transport and human settlements has after numerous delays set a 2025 target for the completion of a concrete wall to bolster border security along the SA-Mozambique border.
The department was earlier this year tasked with fast-tracking the raising of the “jersey barrier” walls in Manguzi, northern KwaZulu-Natal, having been initiated in 2018 as an intervention to curb cross-border crime.
A jersey barrier is a modular concrete or plastic barrier used to separate traffic lanes.
Providing updates on the construction on Wednesday, MEC Siboniso Duma said they had made great progress.
“A new contractor was appointed after the previous contractor defaulted on his contractual obligation and the department had no option but to terminate the contract,” he said. “There is great progress and we should be done, if everything goes accordingly, by next year. We are projecting the completion in the next few months.”
Duma said facilitating the project had been one of his aims in his first 100 days since assuming office in June.
The 25km operation to construct the barrier is being implemented in three phases:
Duma added the project had to include environmental conditions to lessen the harm to nature and species in the area, which contains many wetlands.
More than 7.4km of concrete barriers have been erected to date, as part of the 8km first phase of the project set to be completed by December.
Duma said the project had already started yielding positive results.
“We have been able to limit the exporting of stolen cars and other goods through KZN and to Mozambique. Last year alone, 30 stolen vehicles a month crossed into Mozambique. This number has been reduced.”
He said securing the border, which has been identified as high risk, was important as uMkhanyakude district municipality under which it falls attracted many tourists and investments.
“There is the SA free-trade zone in place because there is serious trade taking place in that area so we’ve identified the need to protect this area.”
He said Mozambique was helping by posting soldiers to the area.
“Along Umhlabuyalingana there is a permanent presence of the SANDF and from time to time we do roadblocks, and Mozambique does the same. We have intercepted a lot [of illegal goods] … and I think we will see improvement in the near future.”
He said the project had been well received by locals as businesses and individuals had gained subcontracting work and training.
“Through the project, 40 local young people have been trained and given job opportunities under the National Youth Service Programme. In addition, the department has strategically placed one of its candidate engineers, Siphamandla Hlongwane, as a resident engineer for the project. This is part of his professional development, which will see him gain relevant experience for registration as a professional engineer with the Engineering Council of SA (Ecsa).
“This has saved us millions which would have been spent on consultants to manage the project,” Duma said.
Source: TimesLIVE